WASTE / CONTAMINATED SITES

Deconstruction of Kölliken hazardous waste landfill, Switzerland

Project details

Complete dismantling of the hazardous waste landfill in Kölliken, which is located in a residential area. During its operating time, about 300,000m³ (475,000t) of hazardous waste was stored in bags, bins and loose on an area of 33,000m². The professional sampling and sample preparation of the deconstructed waste took place mainly in the black area (contaminated area) and therefore placed special demands on the samplers (wearing special protective equipment and breathing apparatus).

Services IBL:

  • Sampling and processing during deconstruction
  • Complete documentation of the sampling
  • Creation of composite samples
  • Preparation and transport to the on-site laboratory
  • Evaluation of analysis results, determination of disposal routes
  • Transfer of all data into the DMS. Selection and storage of reserve samples and disposal of the sample material.

SIMILAR PROJECTS

Framework contract for engineering and analytical services
In-depth recording of the conversion properties
error: Content is protected !!!